Registering Property in India, Ranchi
BUILDING A WAREHOUSEData as of: January 2006
City: Ranchi
Registration Requirements:
| Procedure 1 | Obtain land use permission |
| Time to complete: | 90 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 2* | Obtain soil test |
| Time to complete: | 3 days |
| Cost to complete: | INR 5,000 |
| Comment: | |
| Procedure 3 | Apply for building permit |
| Time to complete: | 90 days |
| Cost to complete: | included in next procedure |
| Comment: | |
| Procedure 4 | Pay building permit fee and obtain building permit |
| Time to complete: | 1 day |
| Cost to complete: | INR 20,000 |
| Comment: | |
| Procedure 5 | Notify Labor department about commencement of construction work |
| Time to complete: | 20 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 6* | Receive labor inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 7 | Notify the Ranchi Regional Development Authority about the commencement of earth work for foundation |
| Time to complete: | 90 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 8* | Receive foundation inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 9* | Notify the Ranchi Regional Development Authority about the start of laying the roof and basement floor level |
| Time to complete: | 88 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 10* | Receive roof inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 11* | Notify the Ranchi Regional Development Authority about the completion of finishing work |
| Time to complete: | 86 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 12* | Receive finishing work inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 13 | Obtain water and sewage connection |
| Time to complete: | 15 days |
| Cost to complete: | INR 7,500 |
| Comment: | |
| Procedure 14 | Obtain no objection certificate from Fire Department |
| Time to complete: | 10 days |
| Cost to complete: | INR 250 |
| Comment: | |
| Procedure 15* | Receive fire inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 16* | Apply for the use uplift of underground water from Jharkhand Pollution Control Board |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 17* | Obtain no objection certificate from Public Health Department |
| Time to complete: | 10 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 18* | Receive public health inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 19* | Obtain power connection |
| Time to complete: | 180 days |
| Cost to complete: | INR 75,000 |
| Comment: | |
| Procedure 20* | Receive electrical inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 21* | Obtain phone connection |
| Time to complete: | 15 days |
| Cost to complete: | INR 2,500 |
| Comment: | |
| Procedure 22 | Obtain completion certificate |
| Time to complete: | 40 days |
| Cost to complete: | INR 2,500 |
| Comment: | |
| Procedure 23* | Receive final inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 24 | Apply for occupancy certificate |
| Time to complete: | 30 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 25* | Receive final inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: |