Registering Property in India, Bangalore
BUILDING A WAREHOUSEData as of: January 2006
City: Bangalore
Registration Requirements:
| Procedure 1 | Obtain land use permission from Bangalore Metropolitan Development Agency |
| Time to complete: | 25 days |
| Cost to complete: | INR 10000 |
| Comment: | The land use permission must be obtained from Bangalore Metropolitan Region Development Authority if the proposed warehouse is within the jurisdiction of Bangalore Metropolitan Region. |
| Procedure 2 | Apply for building permit and pay initial fee |
| Time to complete: | 1 day |
| Cost to complete: | INR 975 (5% building permit fee at INR 15 per square meter) |
| Comment: | An application in writing is required to be given to the Commissioner of the Corporation of the city of Bangalore accompanied by plans, documents, certificates, etc (as listed below): 1.Title deed/possession certificate (certified copy) 2.A copy of the p |
| Procedure 3 | Obtain approval of plans (building permit) and pay final fees |
| Time to complete: | 30 days |
| Cost to complete: | INR 3900 |
| Comment: | Obtain approval of plans (building permit) and pay final fees |
| Procedure 4 | Notify the labor department about commencement of works |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | The company should send an intimation to the concerned Labor Commissioner, Labor Department informing them the intention of commencing the building construction work at particular site to be given 30 days before the commencement of the work. |
| Procedure 5 | Notify the commissioner of commencement of works |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 6 | Notify Commissioner about completion of earth work for foundation |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | The company should inform the Commissioner, Bangalore Mahanagar Palike about completion of the foundation or footings of walls/columns on the foundation. |
| Procedure 7* | Receive foundation inspection and commencement certificate |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | The Commissioner will inspect the site and verify whether the line out marked for the building is according to approved plans. If the site passed the inspection the Commissioner will issue a commencement certificate. The company shall commence work only a |
| Procedure 8 | Notify Commissioner before the start of laying the roof and basement floor work |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 9* | Receive roof inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 10 | Notify Commissioner about completion finishing work |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | Intimation to be sent to the Commissioner, Bangalore Mahanagar Palike intimating completion of Warehouse which is accompanied by a certificate in Schedule VIII certified by a Registered Architect / Engineer / Supervisor and shall apply for permission to o |
| Procedure 11* | Receive finishing work inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 12 | Obtain no objections certificate from the Karnataka state pollution control board |
| Time to complete: | 15 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 13* | Obtain no objections certificate from Public Health Department |
| Time to complete: | 15 days |
| Cost to complete: | INR 3500 |
| Comment: | |
| Procedure 14* | Apply for sanction of power connection with the Karnataka power transmission corporation |
| Time to complete: | |
| Cost to complete: | INR 60,000 (INR 50,000-100,000) |
| Comment: | |
| Procedure 15* | Receive inspection from the Karnataka power transmission corporation |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 16* | Obtain water and sewage connection from the Bangalore water supply and sewage board |
| Time to complete: | |
| Cost to complete: | INR 317,000 (312,000 for installation at INR 240 per square meter + 5,000 for inspection) |
| Comment: | |
| Procedure 17* | Receive on-site inspection from Bangalore water supply and sewage board |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 18* | Obtain phone connection |
| Time to complete: | 7 days |
| Cost to complete: | INR 800 (there is also a INR 2,000 refundable security deposit) |
| Comment: | |
| Procedure 19 | Obtain occupancy permit |
| Time to complete: | |
| Cost to complete: | INR 2500 |
| Comment: | Subsequent to intimation of completion of the Warehouse the authority shall decide after due physical inspection of the building and intimate the applicant within 30 days of the receipt of the intimation whether the application for occupancy certificate i |
| Procedure 20* | Receive inspection for obtaining occupancy permit |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: |