Registering Property in Bangladesh, Chittagong
BUILDING A WAREHOUSEData as of: January 2006
City: Chittagong
Registration Requirements:
| Procedure 1 | Obtain location clearance from CDA |
| Time to complete: | 7 days |
| Cost to complete: | BDT 1,200 |
| Comment: | |
| Procedure 2 | Obtain certificate of ownership from Tahsil Office |
| Time to complete: | 3 days |
| Cost to complete: | BDT 500 |
| Comment: | |
| Procedure 3 | Obtain certified copy of the land tax payment |
| Time to complete: | 3 days |
| Cost to complete: | BDT 300 |
| Comment: | |
| Procedure 4 | Obtain proof that the warehouse meets city zoning requirements |
| Time to complete: | 7 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 5 | Obtain project clearance from Department of Environment |
| Time to complete: | 30 days |
| Cost to complete: | BDT 1,500 |
| Comment: | |
| Procedure 6 | Obtain construction permission from CDA |
| Time to complete: | 60 days |
| Cost to complete: | BDT 5,000 |
| Comment: | |
| Procedure 7 | Receive pre-construction inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 8 | Receive excavation work inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 9 | Receive foundations work inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 10 | Obtain electricity connection |
| Time to complete: | 15 days |
| Cost to complete: | BDT 10,000 |
| Comment: | |
| Procedure 11* | Receive elecrticiy inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 12* | Obtain water and sewerage connection |
| Time to complete: | 20 days |
| Cost to complete: | BDT 8,500 |
| Comment: | |
| Procedure 13* | Receive water inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 14* | Obtain fixed telephone line |
| Time to complete: | 15 days |
| Cost to complete: | BDT 7,500 |
| Comment: | |
| Procedure 15 | Obtain fire inspection certificate |
| Time to complete: | 15 days |
| Cost to complete: | BDT 700 |
| Comment: | |
| Note: Procedures sometimes take place simultaneously. Instances of this are marked with an asterisk (*). | |